What are the costs and fees in the DMA?

Suggestion/Report Error


The development management agreement (DMA) clarifies what constitutes development costs and assigns responsibility for incurring them.  Total development costs, which are borne by the developer, include construction costs and other development/project costs.

Broadly, construction costs are those costs incurred through the actual construction of a built asset, including building design and construction fees.  The costs are often determined by the value established in the construction contract.

Other development/project costs are those costs not directly associated with constructing but that form part of the total development cost.  They include costs incurred for land acquisition, marketing, and planning permits.

The calculation of the development management fee is one of the most important DMA provisions.  The fee can be calculated in various ways, including:

Construction Contracting Fee Example

With excellent execution, contingencies are released and the fee at risk materializing; with worse-than-expected execution, the margin erodes because of additional cost incurred as a result of poor performance of the contractor; and outright poor execution results in the manifestation of multiple risks.

Source: Patricia Galloway

With excellent execution, contingencies are released and the fee at risk materializing; with worse-than-expected execution, the margin erodes because of additional cost incurred as a result of poor performance of the contractor; and outright poor execution results in the manifestation of multiple risks.

Development managers may undertake the construction themselves or appoint contractors to carry out the works.  When also acting as contractor, the development manager earns the respective fee.

Profit sharing programs may be used to incentivize the development managers and the developer's management team, including the CEO, CFO and chief estimator.  External project managers and contractor’s would only profit from the process of carrying out the works, not from the project itself.

To achieve the maximum sustainability of development projects, knowledgeable and experienced development managers must be engaged and paid a commensurate development management fee.  Their managerial skills greatly influence the success of sustainable development projects.